The construction fences are gone from 4th Street. The City of Loveland announced on November 9 that work has wrapped on the five main blocks of its historic downtown, between North Washington and Garfield avenues, ending a rebuild that began in February 2025 and closing out a plan the city says was more than 20 years in the making.

The project is called the Heart Improvement Plan, or HIP Streets, and it is a joint effort of the city and the Loveland Downtown Development Authority. It cost $24.5 million.

What is different on the street

The parts a visitor will see, according to the city:

  • Wider sidewalks set with decorative brick pavers.
  • Curbs and ramps built to Americans with Disabilities Act standards.
  • Seating made from boulders, and lighting scaled for people on foot.
  • New trees and landscaping.
  • More room for pedestrians and for events held in the street.

The city says the extra room did not come out of parking: downtown has the same number of spaces it had before the work started.

What is different under it

Much of the project is out of sight. The city describes the system that ran beneath 4th Street as aged, undersized or deteriorating, with stormwater connections made of clay pipe in places and cast-iron water pipes more than a century old. Crews replaced it with new storm drains and gutters, new water pipes and underground power lines with more capacity, and added fire hydrants and fire lines.

Nearly every city department had a part in the work. Shelley Aschenbrenner of the Public Works Department was the civil project engineer. In the city's announcement she described the challenge of the corridor as fitting modern infrastructure into a street lined with historic buildings without changing its character. Sean Hawkins, executive director of the Loveland Downtown District, said the finished street gives people more ways to shop, eat and gather downtown.

Ten sculptures arrive in spring

One piece is still to come. Ten large sculptures, two on each block, are scheduled to be installed this spring. The series is titled Bloom and is by the artist Jen Lewin. Each sculpture is a cluster of overhead petals that change color in response to the movement of the people around them. The city's Art in Public Places program commissioned the work.

The ribbon cutting for the whole project is being held until the sculptures are in place.

How it was paid for

Of the $24.5 million, $12 million came from the City of Loveland's utility enterprise funds and $12.5 million was financed by the Downtown Development Authority. The city says no General Fund dollars were used.

Seeing it

The rebuilt blocks run through the center of downtown Loveland, in Larimer County, and the city is encouraging residents to walk them during the holiday season. Updates on the sculpture installation and the date of the ribbon cutting will be posted at lovgov.org/HIPStreets.